Case Study · Sand & Fill

Sugar Land Mixed-Use

Sugar Land, TX · 2024

6,800yards moved
19days on site
Construction sand + fill dirtmaterial
Sugar Land Partnersclient

The job

Pad prep for a mixed-use retail and residential project. 6,800 yards of select fill and construction sand over 19 working days.

The site sat against a residential street with a 7am noise restriction, so we staged trucks off-site and rolled at the bell. Zero noise complaints, zero late starts.

Tickets reconciled on the first review. Client signed off without a single dispute.